Steve Scott
I have a six month project with projected spend data for the six individual
months. The costs are budget figures only and are not based on estimated
resources. Is there anyway I can create a task in project with a duration of
six months and a total cost of £x and then be able to go into Task usage View
and edit the spread costs at the monthly level? If I was using resources it
would let me do this by altering the work in each month, but we are not
considering resources here.
This is for a conceptual op-down portfolio Schedulling model.
Thanks in advance.
months. The costs are budget figures only and are not based on estimated
resources. Is there anyway I can create a task in project with a duration of
six months and a total cost of £x and then be able to go into Task usage View
and edit the spread costs at the monthly level? If I was using resources it
would let me do this by altering the work in each month, but we are not
considering resources here.
This is for a conceptual op-down portfolio Schedulling model.
Thanks in advance.