Another question. We have been on this project since July and yesterday the
client sent an email wanting us to do this spreadsheet by month to show
progress going back to July. I can't seem to get a report out of project
that will show budget, actual time, percentage complete, ect by month. When
I try to sort by date the July comes out ok but then Aug just add July and
Aug numbers. Is there a way to get this information for prior periods of
time?
 
J

Jan De Messemaeker

Hi,

No report, but eithe rof the Usage vciews can do that; set the minor
timescale to months and through format, detail styles put in the lines you
need.