G
ghaynestx
I am using Project 2000 and I would like to write a macro (or VB script) that
will copy the values from Remaining Work to Duration1. I want to be able to
save off the remaining work once a week to perform a comparison from one week
to the next. I'm a complete noob though - and can't figure out how to do it.
Any help, examples or direction would be greatly appreciated!
Thanks,
Grace
will copy the values from Remaining Work to Duration1. I want to be able to
save off the remaining work once a week to perform a comparison from one week
to the next. I'm a complete noob though - and can't figure out how to do it.
Any help, examples or direction would be greatly appreciated!
Thanks,
Grace