MS Project 2003 Duration

M

mukulbhind

Hi,

I am using MS-Project 2003, I have much confusion between
*Duration,Actual Duration and Baseline Duration*.
Please help me to explain difference between these values.

Thanks,
Mukul
 
J

Jan De Messemaeker

Hi,

Duration: time difference between start and finish (during Working time)
Actual Duration: time (during Working Time) during which there has been any
work on the task
Remaining duration: Duration - Actual Duration
Baseline Duration: Duration at the time a baseline was set or recorded
through Tools, Tracking, Save Baseline.
 