Hi All,
in MS Project 2003 Report, The current, Resource Hours Worked report,
shows the cumulative Hours for all resources, But I would like to see
the totals for each resources when I generate for all resources. how
can i do this.
any idea very helpful for me..
Thanks,
Mukul
 
J

John

mukulbhind said:
Hi All,
in MS Project 2003 Report, The current, Resource Hours Worked report,
shows the cumulative Hours for all resources, But I would like to see
the totals for each resources when I generate for all resources. how
can i do this.
any idea very helpful for me..
Thanks,
Mukul

Mukul,
What exactly is the "resource hours worked report"? If you are using
Project 2003 Pro as part of Project Server, then you would get a better
answer by posting to our sister newsgroup,
microsoft.public.project.server.

If you are not using Project Server, I suggest you use the Resource
Usage view directly instead of a built-in report. If you display
Cumulative Work in the timescaled data on the right, it will
automatically sum up for each resource.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top