MS Project 2003 Server - Automatic Approvals

C

CLos

Does anyone know how to do automatic approval of time entered through PWA?
Meaning no need for project manager to go in via "Updates" page in PWA and
hit 'accept all' and 'update'.
 
D

Dale Howard [MVP]

CLos --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
you can't within the default options available in Project Server 2003. The
best your PM's can do is to create one or more Rules, but then they still
must click the Run Rules Now button. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top