Hi Asif
Go to the task information dialog by double clicking on it.
Now in the general tab uncheck the estimated check mark.
Apart from this you can also overwrite the duration without the ? mark sign
If you want to put it off permanantly for all new tasks select options from
the tools menu, select the schedule tab and uncheck the last check box which
reads
'New tasks have estimated duration'
Hope this helps