Hello Zodwa,
In order for earned value data to be calculated you must have the
following:
Resources with costs (even $1 per hour will do) - unsure if you have
done this
Resource assigned to tasks - unsure if you have done this
Baseline saved - Done
Actual Data enter - Done
Earned value data is also calculated based upon either the current date
or the status date. If you are entering actual data from past dates,
make sure you also update the status date to the correct date. If there
is no status date, project will use the current date. Check Project >
Project Information.
I hope this helps. Let us know how you get along.
Julie