M
MS Project dosn´t permit several schedul
Project doesn´t permit modify the number of hours per day/week. It´s a
limitant to schedule a project where are several companies that work
diferents schedule.
Example in a project:
- The civil designs are developed daily from Monday to Friday 8 hours per day.
- The civil construction is developed daily 9 hours per day.
Thanks
William
limitant to schedule a project where are several companies that work
diferents schedule.
Example in a project:
- The civil designs are developed daily from Monday to Friday 8 hours per day.
- The civil construction is developed daily 9 hours per day.
Thanks
William