MS Project manage several calendars but the hours per day/week no

  • Thread starter MS Project dosn´t permit several schedul
  • Start date
M

MS Project dosn´t permit several schedul

Project doesn´t permit modify the number of hours per day/week. It´s a
limitant to schedule a project where are several companies that work
diferents schedule.
Example in a project:
- The civil designs are developed daily from Monday to Friday 8 hours per day.
- The civil construction is developed daily 9 hours per day.
Thanks
William
 
M

Mike Glen

Hi William,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #12 on working patterns, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP


"MS Project dosn´t permit several schedul" <MS Project dosn´t permit several
(e-mail address removed)> wrote in message
news:[email protected]...
 
J

Jim Aksel

Project allows you to assign different calendars at the task and resource
levels.
Tools/Change Working Time....

Create a new calandar and then assign that callendar to tasks as appropriate
 
S

Steve House

The 'hours per day' and 'hours per week' numbers on the Calendar Options
page are conversion factors serving only to allow you to enter durations in
your preferred convenient units and they don't affect calculations or
calendars in any way. Durations are ALWAYS stored and tracked in minutes
(actually 1/10 minute 'ticks') and whenever you enter a duration of X days
it is converted to minutes based on X * 'hours per day' setting * 60 minutes
per hour. So if the word 'day' means some different number of hours to a
contractor or to a particular department than it does to the rest of your
company, simply do the conversion in your head rather than having Project do
it for you and enter the required hours in the duration column.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"MS Project dosn´t permit several schedul" <MS Project dosn´t permit several
(e-mail address removed)> wrote in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top