H
Hadi
Experts,
This is more of a comment that a question and I know this has been discussed
on this forum many times. I don't understand why Project (2007 or 2010) wont
allow us to define hours per day for each calendar rather than using the
Tools-->Options-->Calendar to use on all Calendars. I understand that it's
only a conversion factor but still. My schedules have Engineering and
Construction tasks. for Engineering tasks, I'm using the standard 8-5
calendar. So when I punch in 1 day for the duration i want MS Project to show
me 8-5 which what it shows me now. Construction tasks however use 5-10's work
schedule (8am-7pm) with 1 hr lunch. So, when I punch in 1 day for those tasks
I'd like Project to show 8-7 not 8-5. Nor I want to use a 1.25d to get it to
show the 8-7. I don't see why any Project needs to have a universal
definition of a "day". I really hate this
Thanks
Hadi
This is more of a comment that a question and I know this has been discussed
on this forum many times. I don't understand why Project (2007 or 2010) wont
allow us to define hours per day for each calendar rather than using the
Tools-->Options-->Calendar to use on all Calendars. I understand that it's
only a conversion factor but still. My schedules have Engineering and
Construction tasks. for Engineering tasks, I'm using the standard 8-5
calendar. So when I punch in 1 day for the duration i want MS Project to show
me 8-5 which what it shows me now. Construction tasks however use 5-10's work
schedule (8am-7pm) with 1 hr lunch. So, when I punch in 1 day for those tasks
I'd like Project to show 8-7 not 8-5. Nor I want to use a 1.25d to get it to
show the 8-7. I don't see why any Project needs to have a universal
definition of a "day". I really hate this
Thanks
Hadi