Alka said:
can one change the start field from date to time in ms project
Alka,
If you mean to show the time only, then no. The Start field will always
have a date because a date is required to truly define a point in time.
If on the other hand you wish to show the time in addition to the date,
go to Tools/Options/View tab and pick a Date Format that includes time.
I suppose if for some strange reason you really wanted to just show the
time only, you could set up a custom field with a formula that strips
out the time portion of the Start field and shows it.
Hope this helps.
John
Project MVP