multiple baseline compare

M

MAT

Hi..
i have 4 baselines (B,B1,B2,B3).

1) What should i do in order to compare Bi with Bj (2 Baselines)
2) How can i compare the actuel values with Bi (i=1,2,3 and not the comman
Baseline)

Thx...
 
J

Jan De Messemaeker

Hi,

Compare how?
As a figure in a field or graphically in something like a tracking gantt?
 
J

Jan De Messemaeker

Hi,

1. To compare two dates (for instance two baselinestartx)
Tools, Customize, Fields, select a number field
Activate Formula
[Baselinestartx]-[Baselinestarty] returns a value in days
projdatediff( [],[], Calendar name) returns a value in minutes
When you select a duration field projdatediff will be expressed in the
normal duration units

2. To show nonstandard bars in the Gantt Chart (such as haveing a hape to
indicate Baselinestart7 or a bar between baselinestart5 and Start)
see
http://www.mvps.org/project/faqs.htm

Faq 31. Customizing Task Bars

HTH
 