Is it possible to show multiple progress bars, for mutiple starts and
finishes? i.e.: start1 to finish1.
 
J

Jan De Messemaeker

Hi,

Yes, absolutely
Format, Bar Styles
Add a bar description below
Select for which tasks in For...
In From and To set Start1 and Finish1

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional