Multiple projects and master

N

NSkuse98

I have mutiple projects created individually. The tasks for these seperate
projects are linked. How can I create a master schedule with all my projects
without changing the links? Also can I sort my tasks by date without
changing how the tasks are linked?
 
J

Jan De Messemaeker

Hi,

Inserting into a master or Sorting will not modify any link, rest assured.
 
J

John

NSkuse98 said:
I have mutiple projects created individually. The tasks for these seperate
projects are linked. How can I create a master schedule with all my projects
without changing the links? Also can I sort my tasks by date without
changing how the tasks are linked?

NSkuse,
When you say that several tasks are linked between the individual
projects, I assume you are referring to external predecessors and
successors. If you are using some other type of link, we need to know
that.

The simplest way to create a master is by first opening a new project
and then going to Insert/Project and selecting each of the individual
projects. The default is for a dynamically consolidated master so all
the links between projects will be preserved. Once the master is created
you can sort as you normally would - in this case by [whichever] date.

Hope this helps.
John
Project MVP
 