P
PenE
Does anyone have any tips and tricks for handling calendars in MS Project?
Or a best practice guide?
We have a senior level manager at my organization that insists that the only
way to get an accurate schedule out of MS Project is to create a calendar for
every schedule that is worked in the company in every country. We have 10
alternate work schedules alone in the US, and then at least 10 more each in 6
different countries. That would mean creating 70 separate calendars on MS
Project Server with the holidays and nonworking times for each and assigning
each resource to each calendar with the project calendar remaining at
"standard". Here's the kicker, most, if not all of these alternate work
schedules average out to 40 hours per week between Sunday-Saturday.
This is mainly for a large IT project that is not scheduled to end until the
end of 2008 and has a project team of over 200. The tasks aren't even
tracked on a day to day basis, rather a weekly basis.
Anyone have any tips or tricks to handle this situation? Our PMO is not
staffed to handle the setup and maint. that this would require.
Thx.
Or a best practice guide?
We have a senior level manager at my organization that insists that the only
way to get an accurate schedule out of MS Project is to create a calendar for
every schedule that is worked in the company in every country. We have 10
alternate work schedules alone in the US, and then at least 10 more each in 6
different countries. That would mean creating 70 separate calendars on MS
Project Server with the holidays and nonworking times for each and assigning
each resource to each calendar with the project calendar remaining at
"standard". Here's the kicker, most, if not all of these alternate work
schedules average out to 40 hours per week between Sunday-Saturday.
This is mainly for a large IT project that is not scheduled to end until the
end of 2008 and has a project team of over 200. The tasks aren't even
tracked on a day to day basis, rather a weekly basis.
Anyone have any tips or tricks to handle this situation? Our PMO is not
staffed to handle the setup and maint. that this would require.
Thx.