When inserting a sub-project into a master project, tasks which have Must
Finish On (MFO) are overridden, and their Finish Date changed.
Is it possible to prevent this, so that the master project honors MFO
constraints in sub-projects?
Finish On (MFO) are overridden, and their Finish Date changed.
Is it possible to prevent this, so that the master project honors MFO
constraints in sub-projects?