I have several projects that are in process at the same
time, what i do is i import all the projects into one
project, but here is the problem, the resources
are not allocating themselves properly. To give you an
example You have one resource lawn mover, project number
one is mowing lawn one project number two is mowing
lawn two but there is only one lawn mower. When imported
into one project the lawn mower should mow lawn one and
then two but it mowing both of them simultaneously, how
should i structure the project that each resource i.e.
lawn mower, tillar, weed eater should schedule properly and
automatically while working on maybe 20 to 30 lawns.
time, what i do is i import all the projects into one
project, but here is the problem, the resources
are not allocating themselves properly. To give you an
example You have one resource lawn mover, project number
one is mowing lawn one project number two is mowing
lawn two but there is only one lawn mower. When imported
into one project the lawn mower should mow lawn one and
then two but it mowing both of them simultaneously, how
should i structure the project that each resource i.e.
lawn mower, tillar, weed eater should schedule properly and
automatically while working on maybe 20 to 30 lawns.