TROYBAL
Looking for some help using Microsoft Project Professional 2003.
Need a simple High Level resource chart to track where Engineers are located.
Example.
My Tasks may be building houses.
So I have 10 houses to build.
So Task #1 = House #1
Task #2 = House #2
And so on....
I know that House #1 task is going to be 6 Months regardless of how many
Engineers are there.
I have 15 Resources(Engineers), I want to assign 2 Engineers to House #1,
regardless
of what they do..
And 3 Resources to House #2. etc....
I need to be able to see the 2 Engineers(House #1 Task) as a single line
which would include there vacation time, holidays, etc....
Each Engineer as a single line, not all on the same line.
Simple high level view
But I am having difficulty figuring this out.
Thanks
TR
Need a simple High Level resource chart to track where Engineers are located.
Example.
My Tasks may be building houses.
So I have 10 houses to build.
So Task #1 = House #1
Task #2 = House #2
And so on....
I know that House #1 task is going to be 6 Months regardless of how many
Engineers are there.
I have 15 Resources(Engineers), I want to assign 2 Engineers to House #1,
regardless
of what they do..
And 3 Resources to House #2. etc....
I need to be able to see the 2 Engineers(House #1 Task) as a single line
which would include there vacation time, holidays, etc....
Each Engineer as a single line, not all on the same line.
Simple high level view
But I am having difficulty figuring this out.
Thanks
TR