I am trying to link tasks in two separate projects, both saved and published
to Project Server. I am using Project Professional 2007.
The instructions in MS Project Inside Out say to type,
"<>\[projectname].mpp.published\[tasknumber]" or
"<>\[projectname].mpp.published1\[tasknumber]" (depending upon the enterprise
version control protocol?) into the ID field of the Task Information window
in the Predecessors tab.
I have tried every variation of this that I can think of, with no success.
Does anyone know how to link tasks between two separate projects?
Thanks,
Dave
to Project Server. I am using Project Professional 2007.
The instructions in MS Project Inside Out say to type,
"<>\[projectname].mpp.published\[tasknumber]" or
"<>\[projectname].mpp.published1\[tasknumber]" (depending upon the enterprise
version control protocol?) into the ID field of the Task Information window
in the Predecessors tab.
I have tried every variation of this that I can think of, with no success.
Does anyone know how to link tasks between two separate projects?
Thanks,
Dave