Need to view baseline work in master project schedule

T

tnew

I have 60 projects linked into one master project and when I insert the
baseline work column there are 0 hours displayed when I collaspe the project.
If I expand the schedule I see them but not on the summary line.
 
M

MSP Angel

Make sure you have all the subprojects opened, make sure you highlight all
and "Show All Subtasks" select this twice and hit F9 (calculate) 2 or 3 times
making sure the "calculate" is gone in the "reay" window in the bottom left
of your screen. Otherwise if this dosent solve your issue, try creating a
View with the specific comumns and see if that gives you the results you're
looking for.
 
J

JulieS

Hello Tnew,

When you insert tasks into a master the Inserted Summary Project line is
created automatically by Project. In order to show the baseline data
you would need to baseline those tasks within the master.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 