I'm trying to develop a cash flow report against a virtual cube -
MSP_Project_Timesheet. Everything works great. However, when posting
negative baseline costs in MS Project 2007 it doesn't post
MSP_Project_Timesheet. It posts the changes to the Assignment Non Timephased
cube. It appears positive baseline costs show up correctly in
MSP_Project_Timesheet. I've downloaded the SDK and I'm currently looking at
the OLAP schemas for more information. Any help in the right direction would
be greatly appreciated.
MSP_Project_Timesheet. Everything works great. However, when posting
negative baseline costs in MS Project 2007 it doesn't post
MSP_Project_Timesheet. It posts the changes to the Assignment Non Timephased
cube. It appears positive baseline costs show up correctly in
MSP_Project_Timesheet. I've downloaded the SDK and I'm currently looking at
the OLAP schemas for more information. Any help in the right direction would
be greatly appreciated.