B
bbcrock
I could not find this in the help file, just so you know I looked.
I have resource hourly costs. I have a firm budget. In about half my
tasks I have a firm due date. Much of my work estimates show that
we're going to need to have double or triple-staffed tasks requiring
detailed WBS's and critical path analysis to be able to meet those
dates. I want to display in a standard Gantt chart view the budgetary
limit (which I have in a custom field) and the cost estimate (I expect
it will take 3 resources 160 hours each to complete this at $80, $85
and $110 per hour). I cannot seem to get that cost estimate to
display. Our VP wants to move resources in real-time and see the
effect on the estimated real budget vs our total budget. Is this a
custom field I must create? I feel silly because thought I created
this about 8 years ago.
thanks,
Don
I have resource hourly costs. I have a firm budget. In about half my
tasks I have a firm due date. Much of my work estimates show that
we're going to need to have double or triple-staffed tasks requiring
detailed WBS's and critical path analysis to be able to meet those
dates. I want to display in a standard Gantt chart view the budgetary
limit (which I have in a custom field) and the cost estimate (I expect
it will take 3 resources 160 hours each to complete this at $80, $85
and $110 per hour). I cannot seem to get that cost estimate to
display. Our VP wants to move resources in real-time and see the
effect on the estimated real budget vs our total budget. Is this a
custom field I must create? I feel silly because thought I created
this about 8 years ago.
thanks,
Don