D
dave
I have some task on a project that require staff to spend
say 20% of there time. If I set this tasks reasource usage
to 20% other tasks that are set as 100% will not fill the
time automatically. If I manually set the task to 80% then
it will, but this means I need to know which task is
likely to be at the same time as the 20% task. Is there a
checkbox/option that will allow project to change the
reasource units on a task and extend the time to allow
that task to be performed over the same period as the
first task.
thanks
dave
say 20% of there time. If I set this tasks reasource usage
to 20% other tasks that are set as 100% will not fill the
time automatically. If I manually set the task to 80% then
it will, but this means I need to know which task is
likely to be at the same time as the 20% task. Is there a
checkbox/option that will allow project to change the
reasource units on a task and extend the time to allow
that task to be performed over the same period as the
first task.
thanks
dave