A
Aj
Hi. I have recently encountered a problem that I hope has an easy solution. I
use MP as a schedule for my business (construction) which has many "rainy
days" where work can not be done at all. When I go into the calender to save
these days as non working days, I would like to know if there is a way to
have the computer automatically extend the duration date by however many
workdays I have lost. Thanks!
aj
use MP as a schedule for my business (construction) which has many "rainy
days" where work can not be done at all. When I go into the calender to save
these days as non working days, I would like to know if there is a way to
have the computer automatically extend the duration date by however many
workdays I have lost. Thanks!
aj