R
roger.books
Hello all,
I have a resource which I set up to have 4 people (units). I then
setup a Fixed Work Task, assigned it 30 days, and added the 4 units of
the resource to rhis task. The duration, as expected, dropped to 7.5
days.
I want to display that I am allocating 4 units on the Gaant Chart on
the printout. I have spent the last hour trying to find the
appropriate column to add. Can anyone tell me what it is?
TIA,
Roger Books
I have a resource which I set up to have 4 people (units). I then
setup a Fixed Work Task, assigned it 30 days, and added the 4 units of
the resource to rhis task. The duration, as expected, dropped to 7.5
days.
I want to display that I am allocating 4 units on the Gaant Chart on
the printout. I have spent the last hour trying to find the
appropriate column to add. Can anyone tell me what it is?
TIA,
Roger Books