odd date level by project

G

greg tatchell

can anyone assist with why project would throw an inserted project out to
2049. even when there are no tasks conflicting with this?
 
J

Jan De Messemaeker

Hi Greg,

Assigning to a task a resource whose availability is 0 does that.
Check the availability profile of the resources.
Rempember that when you put as only data in there that the resource works
f.i. 50% from date A to date B, for the remainder of eternity it is not
available.
HTH
 