SuzMills
I have a resource that is only available for 35% of her time, my task is a 20
hour task, I have flagged her units for the task at 35%, her work day is 8
hours giving approx 2.8 hours per day to do the 20 task that means the
duration should be around 7 days, however my plan shows the task duration of
Aug 15 - Aug 17. I have no date constraints - what am I doing wrong