S
sdesomer
First of all I do not have Project Server so can't create one of their Admin
Projects.
So, I have work being done that can't be scheduled (typical admin stuff,
pre-analysis consulting, continuity issues, etc.). This work needs to be
accounted for for a couple of reasons: 1) I want to account for the work and
its inherent cost, 2) I want to be able to schedule the average amount of
time a resource spends doing it.
Subtracting from Resource Availability satisfies #2 but not #1. Creating a
task of indeterminate length kind of satisfies both #1 and #2, but the task
is unwieldy. How does anyone out there do it.
Thanks
Projects.
So, I have work being done that can't be scheduled (typical admin stuff,
pre-analysis consulting, continuity issues, etc.). This work needs to be
accounted for for a couple of reasons: 1) I want to account for the work and
its inherent cost, 2) I want to be able to schedule the average amount of
time a resource spends doing it.
Subtracting from Resource Availability satisfies #2 but not #1. Creating a
task of indeterminate length kind of satisfies both #1 and #2, but the task
is unwieldy. How does anyone out there do it.
Thanks