M
Mark Dietrich
Background: I am setting up the structure for a master project with 8-10
subprojects that will be inserted into the master (dynamically). I am using
MS Project Standard 2003 SP2 but am more than willing to upgrade to 2007 or
Project Server if it will solve some of my issues. It is for a large IT
Program that will need to incorporate the typical 5-6 phases;
Plan/Analyze/Design/Build/Implement/Operate
and typical streams of work based on a WBS;
PMO/QA/Functional/Arch/Config&Dev/etc
Challenge:
1. What is the preferred method for organizing the Program such that each
work stream has a single subproject plan to update each week that also allows
for a clear view by "phase" at the Master level?
Note: From what I have researched thus far my options are to have 5 plans
for each work stream covering each phase which is crazy to maintain OR create
some sort of customized field/view/grouping/filter that would allow a view to
be filtered by phase but I suspect implementing this would pose challenging
to say the least. Please provide alternatives I may not have thought of...
2. Is it possible to insert i) a subproject at a specified outline level
(ie. only level 3 and above)? or ii) a portion of a subproject but not the
whole thing (ie. a single phase)?
I am hopeful this is a common challenge but didn't see anything on the
discussion board other than how to use some customized fields as a work
around. Help please
subprojects that will be inserted into the master (dynamically). I am using
MS Project Standard 2003 SP2 but am more than willing to upgrade to 2007 or
Project Server if it will solve some of my issues. It is for a large IT
Program that will need to incorporate the typical 5-6 phases;
Plan/Analyze/Design/Build/Implement/Operate
and typical streams of work based on a WBS;
PMO/QA/Functional/Arch/Config&Dev/etc
Challenge:
1. What is the preferred method for organizing the Program such that each
work stream has a single subproject plan to update each week that also allows
for a clear view by "phase" at the Master level?
Note: From what I have researched thus far my options are to have 5 plans
for each work stream covering each phase which is crazy to maintain OR create
some sort of customized field/view/grouping/filter that would allow a view to
be filtered by phase but I suspect implementing this would pose challenging
to say the least. Please provide alternatives I may not have thought of...
2. Is it possible to insert i) a subproject at a specified outline level
(ie. only level 3 and above)? or ii) a portion of a subproject but not the
whole thing (ie. a single phase)?
I am hopeful this is a common challenge but didn't see anything on the
discussion board other than how to use some customized fields as a work
around. Help please