S
Sally
As opposed to using outlining columns, I am using task outlining both for
legability, indenting the number with the txt, printing and export reasons.
However I need each sub-project to start with a different number. Currently
I am using blank tasks to force the numbering.
Using Outlining in the text, can I define a start number?
When I place a sub-projects into a master project the sub numbers all
commnece with 1.
Can I retain the outline numbers so that tasks under "7.0 Project name "
expands to 7.1, 7.1.1, etc?
Thanks,
Sally.
legability, indenting the number with the txt, printing and export reasons.
However I need each sub-project to start with a different number. Currently
I am using blank tasks to force the numbering.
Using Outlining in the text, can I define a start number?
When I place a sub-projects into a master project the sub numbers all
commnece with 1.
Can I retain the outline numbers so that tasks under "7.0 Project name "
expands to 7.1, 7.1.1, etc?
Thanks,
Sally.