A
assaf1978
Hi,
I have defined that each day's work is 9 hours. But when I insert a task
that is only for 1 day it shows (in the resource sheet) two days, the first
is 8 hours and the second is 1 hour.
I guess this is due to the 1 hour break that is defined in the calendar.
How do I cancel that break , assuming this is the cause.
If not, how do I make the resource not turn red for 9 hours?
Thanks,
Assaf.
I have defined that each day's work is 9 hours. But when I insert a task
that is only for 1 day it shows (in the resource sheet) two days, the first
is 8 hours and the second is 1 hour.
I guess this is due to the 1 hour break that is defined in the calendar.
How do I cancel that break , assuming this is the cause.
If not, how do I make the resource not turn red for 9 hours?
Thanks,
Assaf.