K
KT
I am having an overallocation problem when I assign a single resource for
multiple tasks. Say for example, Eric is assigned to two projects (Project A
& Project B), each takes 20hrs to complete and they come in on the same day.
But project B has a high prority that project A. So when assigned, I want
Eric to first work on the high priority project and then start with the
other one. When I assign things in project, it makes Eric work on both of
them (more number of hours for the high priority project and less on the
other) with a overallocation notice. Is there a solution to this?
multiple tasks. Say for example, Eric is assigned to two projects (Project A
& Project B), each takes 20hrs to complete and they come in on the same day.
But project B has a high prority that project A. So when assigned, I want
Eric to first work on the high priority project and then start with the
other one. When I assign things in project, it makes Eric work on both of
them (more number of hours for the high priority project and less on the
other) with a overallocation notice. Is there a solution to this?