Hi Confused,
Sorry for the delay in responding. I'm glad to know things are a bit
clearer about the overtime work/cost questions and thanks for the
feedback.
To your new question about Max. Units. I'm sure you'll get other
opinions on this one but as you asked, here's my thoughts and comments.
You note the instructor told you not to fill in max. units. I assume
the instructor meant to leave the unit to the default of 100% and not to
drop the max. units fields below 100% to reflect that a resource cannot
devote "full time" to a project.
If a resource truly only works part time (they work 4 hours per day on
Monday through Friday) I would most definitely change that resource's
calendar with the specific 4 hours per day they work and *possibly*
leave the max. units at 100%. By changing the resource's calendar, I am
restricting the times the resource can work on tasks. If a task is
scheduled to start at 3:00 pm and Bob is the sole resource assigned but
he only works from 8:00 am to 12:00 pm, the task start will change to
8:00 am the next day reflecting Bob's working calendar.
On the other hand, I *do* use max. units of less than 100% quite
frequently to reflect that a resource cannot gernerate one hour of
effort on project tasks for each one hour of working time in the
resource's calendar. The max. units field is the default assignment
value used by Project when resources are assigned. By setting the max.
at less than 100% and entering the work estimate a resource has given
me, Project will divide the work estimate by the max units and calculate
a duration for the task. So, for example, if the resource Sue works 40
per week, but my project sponsor says I can only have half of Sue's time
(approximately 20 hours per week). I would set Sue's max. units at 50%.
Then in reviewing a work package with Sue, she tells me task G is 20
hours of work. If I assign Sue to a 20 hour work task, Project will
calculate a task duration of 1 week (40 hours).
As I said, you will most likely get other opinions as well
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
Confused said:
JulieS:
Thanks for responding. It took me awhile to get back into this. I
get how
this works and I appreciate your help. Can I add one question? Do
you ever
change the max units field on the resource sheet? I took a class and
the
instructor warned us to let project calculate that field and use a
resource
calendar to reflect a part time employee (rather than addding 50% into
that
field). Do you agree with that comment, and if so why? Thanks so
much for
your help. I hope I can figure this application out!--
Thanks.
Confused