I have an overallocation problem. Scenario is:
Task A is 10 days (Allocated to person X)
Task B is 1 day task (fixed for a given day that occurs in parallel with
Task A - and is also allocated to person X)
Task A therefore needs to extend its duration by 1 day. However, what
actually happens is that on that particular day, person X is over allocated
(200%)
Is there an automatic way of handling this scenario. If not, how should it
be handled.
Thanks in anticipation.
Mark