Parallel tasks in same project by same person

M

Marko

I have an overallocation problem. Scenario is:
Task A is 10 days (Allocated to person X)
Task B is 1 day task (fixed for a given day that occurs in parallel with
Task A - and is also allocated to person X)

Task A therefore needs to extend its duration by 1 day. However, what
actually happens is that on that particular day, person X is over allocated
(200%)

Is there an automatic way of handling this scenario. If not, how should it
be handled.

Thanks in anticipation.
Mark
 
J

Jan De Messemaeker

Hi,

Tools, Resource Leveling handles this
Make sure the option Leveling cansplit tasks is ON.
HTH
 
D

DonL

Marko,

If you have "Level only within available slack" checked, you should try
leveling after un-checking it, as this might force the longer task to remain
in its pre-leveled time frame if not enough slack exists in your plan for it
to move without affecting the project's end date.

Hope this helps! :)
 
M

Marko

Thanks very much for your help. It worked!
I know all this is in the manual, but it's not always obvious where to look.
Mark
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top