Hi,
I'm trying to set up a project using MS Project 2003, but I can't
really understand how to manage part time resources.
Say I have a task which is planned to take 40 hours. If I assign a
regular 40 hour per week resource to that task, it will take one week.
But how to I specify a resource which will always work only 4
hours/day?
Then if a assign that part time resource to the 40 hour task, I expect
it to take 2 weeks.
/Jarl