D
David Oliver
It seems MSP uses % complete rather than % work complete
to compute earned value from planned value for a task or
project. This doesn't make sense to me given that
planned value is work X resource rate and %complete is
really a measure of duration rather than work. It's like
comparing apples and oranges. Using %complete instead of
%work complete also really skews the earned value on
partially completed tasks that have been split during
schedule statusing (Tools/Tracking/Update
Project/Reschedule uncompleted work to start after...)
So I am wondering if MSP provides a configuration option
that allows you to use %work complete to compute earned
value (BCWP), and consequently spi and cpi? Can anyone
help with that? Thanks in advance to anyone who replies
to this question!
to compute earned value from planned value for a task or
project. This doesn't make sense to me given that
planned value is work X resource rate and %complete is
really a measure of duration rather than work. It's like
comparing apples and oranges. Using %complete instead of
%work complete also really skews the earned value on
partially completed tasks that have been split during
schedule statusing (Tools/Tracking/Update
Project/Reschedule uncompleted work to start after...)
So I am wondering if MSP provides a configuration option
that allows you to use %work complete to compute earned
value (BCWP), and consequently spi and cpi? Can anyone
help with that? Thanks in advance to anyone who replies
to this question!