Pinting only one week of a Gantt chart

B

Brad

Hi, I have set up a project that has a duration of about one month. Most of
the tasks take place during one week. I would like to print a Gantt chart
"zoomed in" to that week but I always get the whole timespan of the project
on the printout. I can't find an easy way to print only one selected week.
Does anyone have any advice?
Thanks.
 
J

John

Brad said:
Hi, I have set up a project that has a duration of about one month. Most of
the tasks take place during one week. I would like to print a Gantt chart
"zoomed in" to that week but I always get the whole timespan of the project
on the printout. I can't find an easy way to print only one selected week.
Does anyone have any advice?
Thanks.

Brad,
Go to File/Print and use the "Timescale/Dates" option to set the week
range you want.

John
Project MVP
 
B

Brad

That did the trick - thank you very much.

John said:
Brad,
Go to File/Print and use the "Timescale/Dates" option to set the week
range you want.

John
Project MVP
 
C

Catfish Hunter

You could also set up a filter for task that take place before a date. Go to
Project>Filter>More Filters>New-
and/or Name Test Values
Start is less than or = to "And before:"?
And % Comp Is Less Than 100%

Then hit apply. Projects will ask for an end date.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top