Placing task symbol within gantt task bar

T

tom

Does anyone know how or if I can place a task sympol (i.e.
a triangle) within a task bar, and hopefully label that
individual task as well as the longer duration task? I'm
trying to represent a one-day task within a larger month-
long task on the same line.

thanks
td
 
M

Mike Glen

Hi Tom,

Welcome to the Microsoft Project newsgroup :)

You could use the Drawing tools to do that or you could add a Deadline
marker via the Task information Advanced tab.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 

Ask a Question