G
greenbean
MS Project 2003
I am rebuilding a plan and would like the following but cannot get project
to do it!
e.g. a simple set of tasks that are linked to occur one after each other
task1 then task2 then task3
if each is two days long
task1 starts mon finishes tues 2d
task2 starts wed finishes thu 2d
task3 starts fri finishes sat 2d
How do I get project to display the data this way - what its doing is:
task1 starts mon finishes tues 2d
task2 starts tues finishes thu 2d
task3 starts thu finishes sat 2d
Although they are the same in terms of schedule I want it to read as the
first list. I have set my project up as fixed duration and NOT effort
driven...
Help appreciated greatly
Chris
I am rebuilding a plan and would like the following but cannot get project
to do it!
e.g. a simple set of tasks that are linked to occur one after each other
task1 then task2 then task3
if each is two days long
task1 starts mon finishes tues 2d
task2 starts wed finishes thu 2d
task3 starts fri finishes sat 2d
How do I get project to display the data this way - what its doing is:
task1 starts mon finishes tues 2d
task2 starts tues finishes thu 2d
task3 starts thu finishes sat 2d
Although they are the same in terms of schedule I want it to read as the
first list. I have set my project up as fixed duration and NOT effort
driven...
Help appreciated greatly
Chris