E
ETNPNYS
I apologize up front; I am new to Project, so my questions will hopefully be
ridiculously easy to answer.
I am using Project 2003 Standard. Here is the problem I am experiencing:
1. Create a task [Development] with a Mon-Tues timeline
2. Create a task [Testing] with a Wed-Fri timeline
3. Make Task1 an FS predecessor of Task2
4. Change Task1 so that it ends on Wed
Result: Task2 is STAYING with a start date of Wed, even though its
predecessor has not ended yet!
Expected: Task2 to automatically adjust to start on Thurs and end on Mon
Am I missing something?
ridiculously easy to answer.
I am using Project 2003 Standard. Here is the problem I am experiencing:
1. Create a task [Development] with a Mon-Tues timeline
2. Create a task [Testing] with a Wed-Fri timeline
3. Make Task1 an FS predecessor of Task2
4. Change Task1 so that it ends on Wed
Result: Task2 is STAYING with a start date of Wed, even though its
predecessor has not ended yet!
Expected: Task2 to automatically adjust to start on Thurs and end on Mon
Am I missing something?