S
scott_hanebutt
I have been experimenting with the start-to-finish relationship and am
confused about the way it works. I understand the concept of when to use
this relationship. My problem is the way it acts.
The name implies that predecessor must start before the succesor can end.
It says nothing against the possibility that the predeccesor might finish
before the successor finishes.
I set up a simple trial of this relationship and got unexected results. I
did the following.
TasK1 duration 2 days start date is project start date
Task2 duration 3 days start date is project start date
I then added a start to finish relationship to task 2. At this point
project moved task2's start and finish date before the project start date so
that task 2 ended on the same day that Task1 started.
The way I see it the dates should not have changed. Task1 was already
starting before task2 was finishing.
I am missing something?
Thanks,
Scott Hanebutt
confused about the way it works. I understand the concept of when to use
this relationship. My problem is the way it acts.
The name implies that predecessor must start before the succesor can end.
It says nothing against the possibility that the predeccesor might finish
before the successor finishes.
I set up a simple trial of this relationship and got unexected results. I
did the following.
TasK1 duration 2 days start date is project start date
Task2 duration 3 days start date is project start date
I then added a start to finish relationship to task 2. At this point
project moved task2's start and finish date before the project start date so
that task 2 ended on the same day that Task1 started.
The way I see it the dates should not have changed. Task1 was already
starting before task2 was finishing.
I am missing something?
Thanks,
Scott Hanebutt