plotting BCWS estimates monthly across entire project

J

john

Hi,

Can someone tell me please how I can get the BCWS figures
out of project 2002 so that I can plot a baseline of
monthly planned spend before any actuals are recorded?

Thanks,

John
 
S

Steve House

Set your status date to the project end and use the export timephased data
to Excl tool. Gives you great S curves too <g>.
 