S
Shant Michaelian
Ok, I don't know if this his possible...
I have two tasks:
Task1
Task2
Task2's precedence is Task1. Let's say it takes Task1 4 days to
complete and Task2 has to begin only when Task1 is complete. So if
Task1 takes 6 days, Task2's start date and bar in the Gantt Chart
should move to the right. I can't get this to happen.
What usually happens is that Task1's bar completion runs over the start
of Task2's bar and the arrow snakes around to the start of Task2.
How can I have Task2's start change when Task1 is late?
I have two tasks:
Task1
Task2
Task2's precedence is Task1. Let's say it takes Task1 4 days to
complete and Task2 has to begin only when Task1 is complete. So if
Task1 takes 6 days, Task2's start date and bar in the Gantt Chart
should move to the right. I can't get this to happen.
What usually happens is that Task1's bar completion runs over the start
of Task2's bar and the arrow snakes around to the start of Task2.
How can I have Task2's start change when Task1 is late?