Predecessors & Successors

K

Karen

I'll be setting up small projects in Project 2003 for my
office. We don't have any HUGE projects. My boss wants
us to start using this management tool. Is it important
to set up predecessors & successors in a project? We
really are not using Project to it's fullest capacity
(not even close)- What if I don't set them up?

Thank you
 
P

Project Slave

Technically, nothing is wrong if you don't set predecessors and successors.
It is there for your own convenience.

For example, if you are unable to complete one of the tasks on time, its
successor tasks will automatically move, if you have set it up as successor.
If you don't, you have to manually move it. That is all.

The optimal sequence to create a project plan is to identify tasks >
sequence tasks > estimate duration.
 
D

davegb

The concept of linking the tasks is primarily of use in Critical Path
Method scheduling. While too involved to go into detail here, it
basically helps you to know what tasks are more important (critical)
time wise, the ones that if they slip in time will result in delaying
the end of your project.
Without linking, you'd be doing what is called event driven scheduling,
creating a list of tasks and checking them off as you to them. This
works fine if you're the only one working on the project, or everyone
knows their part and it's relationship to every one elses. Which is
very rarely the case, even with relatively small projects. Just start
asking for the information you need to create the links, and you'll
find out how "out of sync" or "in sync" people really are.
An analogy might be if you had a car with a stick shift. If you didn't
know what the shift lever was for, you could drive around in first all
the time, and pretty much get where you needed to go. But not very
efficiently time-wise or fuel-wise. And you'd be in big trouble if you
parked face in to a brick wall and didn't know how to use reverse!
So if you don't set up dependencies, you end up with a nice list of
tasks with no meaningful end date. My experience is that as the tasks
slip, and in this envrionment, they usually do, we tell ourselves,
"It's ok, we'll make it up on the next task". And seldom do. Then just
as the project is supposed to finish, it comes as a big surprise that
it's going to be late. Go figure!
Some years ago, when a client company's VP was telling me what he
wanted from me as a consultant, he said he wanted to know why he had so
many "100 day projects that were 100 day projects until day 99". In
other words, to achive disciplined results, you need disciplined
procedures.
I suggest you try it without the links and see how useful it is. Then
try it with the links on a few projects. This will take some effort the
first few times. But my guess is, you'll be amazed at what can happen
if you get the thing out of first gear!
Best of luck.
 
S

Steve House [MVP]

And just how are you going to sequence the tasks without using predecessor
links? Sequencing implies something driving the sequence. In Project,
there are two basic reasons that all the tasks can't happen at once -
firstly, some tasks require deliverables to be created that are then used as
input to the task at hand and thus must be done in an order that is
determined by the logic of the process itself; and secondly your resources
can only do so much at once and so tasks must be staggered so that only as
much as can be worked on at any given time is scheduled for that time.
Predecessor linking takes care of the former and task prioritizing coupled
with resource leveling takes care of the latter. Given that Project
scheduling software exists to compute the work schedule for you and you
should not be supplying the dates for individual tasks except in certain
very limited circumstances, links are far more than a mere convenience -
without them your project plan will be be a meaningless muddle, something
you could just as easily have created with a wall planner and box of markers
for a lot less money than a computer with Project installed.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top