Gerard,
Thanks again. Sorry if I was overwrought.
Unfortnately, it is more complicated than I explained. I want to see
completed work before the progress line and uncompleted work after the status
line. This would allow a very straightforward calculation of Work Performed,
When I try to implement this mode is when I have problems. The help, I
believe, tells you that if you use automatic calculate all entered actuals
are erased and Project calculates the actual costs. This is definitely not
what I want. I need to be able to enter actual costs not calculated actual
costs. I have to reflect what is in the financial system not some estimate.
The PM I am working with insists on not entering tasks in any sequence.
Therefore, he can complete work that is out three weeks from the status date.
I need to acquire this work for an accurate BCWS number. The technique I am
using will do this. However, as I explained, when I do it, it adds the BCWP
number to the ACWS which throws that number off! I have to go out to near the
end of the project with the status line to accumulate all BCWP. Then, I have
to go back with the status line to get BCWS correctly. Then I use Actual
Costs instead of ACWP since it is showing about twice the correct number when
it adds in the BCWP.
The function, as explained in three books and the on line and included help,
should do exactly what I want and in the program MS sent me back, it works
perfectly!! (I just went back to my Read Only file that I don't want to lose,
and it does indeed work as advertised. They told me that they had loaded my
program into Project Professional, but other than that I cannot see anything
that they claim they did that is different from what I am doing. I don't
believe I have ever used a program that you can't look up the directions for
how to make it work and it doesn't! This is driving me nuts.
Message from MS
Resolution
=========
· You informed that actual Cost & ACWP (Actual cost work
Performance) field shows wrong Data
· Changed the calculation mode to manual.
· Opened the Project in Question from Project professional
· Click on project >project information >Changed the status Date to
equal to or later than the latest actual work
· Now opened the Task Usage View >Actual cost Collection >Added the
cost (5000+5000+5000+5000)
· Opened Gantt Chat >Press F9
· Now we can see that both the values for ACWP & Actual Cost are
equal.
___________________________________________________________________
I spoke to MS several times, and I am not certain the problem I described
was ever understood. The fellow I talked to didn't seem to understand the
acronyms for Earned Value Analysis.
If you have time, you might set up a program (some old thing) to put
completed work before the Progress Line and Unfinished work after the
progress line. If it works right away, let me know what your Tools, Options
selections are and maybe that will fix my problem. I click all five options
on the "Calculation options for "file name"
Larry (Thanks for your continued interest!)