prevent certain tasks happening on certain dates in project

R

Rick

I have a project involving the refurbishment of a barracks however part way
through the project the barracks will be occupied for a period of training,
during this time access will not be available to the inside of the buildings,
but we can still work on external painting etc.

How can i setup project so that the internal tasks cannot happen during a
certain period bu the external tasks can?
 
J

JulieS

Hi Rick,

Create a calendar (Tools->Change Working Time) and mark the time that the
internal tasks cannot be worked on as non-working time. Assign the calendar
to the internal tasks (Double click on the task and on the advanced tab,
select the calendar.)

Hope this helps. Let us know how you get along.

Julie
 