A
AndyOfNZ
Is it possible to add a series of tasks that depend on the outcome o
another? I've searched various forums about 'what-if' tasks and all sa
the same thing: Add the tasks and save a version for each variant.
That's not much good to me. The scenarios I'm thinking of could happe
a long time away but I would like to plan for them now. I would like t
be able to show the impact should a certain risk occur.
Here's a few examples:
- I have a risk and the plan should the risk occur has been though
out in detail. I want to put the tasks into the schedule so we ca
track what will happen to the project if the risk occurred at an
given time. Let's make it easy and say it might happen at one time
say when the clocks change... did it impact the system's schedule? I
yes, invoke risk plan. While the risk does not happen the dependen
tasks can start. (in reality they aren't always that easy and we nee
to move the risk around in time, keep the dependencies locked in, bu
as it probably won't happen I need to keep the resources available t
start the tasks as if the risk plan wasn't there)
- I am due to go on extended leave in November. If the project doe
not finish in time then I need to schedule handover tasks in October
I would like these tasks to not affect the total cost of the projec
or the overall time line unless a key milestone passes a deadline.
- The project is at risk of exceeding a threshold. We want to look a
reducing scope to meet the threshold. We don't want to lose all th
values for the tasks for a particular deliverable but want t
effectively cancel them to see the impact (I know I could just mov
the tasks to a different phase further down but that will mess up th
tracking views and EVA and is not what I want to show).
I know that I can do a lot of this manually and I can plan for th
worst case every time, but it would be so nice if MS Project could le
me put the scenarios into the schedule and alert me accordingly.
Thanks in advance for any advice that any of you may be able t
provide.
Regards, Andrew
another? I've searched various forums about 'what-if' tasks and all sa
the same thing: Add the tasks and save a version for each variant.
That's not much good to me. The scenarios I'm thinking of could happe
a long time away but I would like to plan for them now. I would like t
be able to show the impact should a certain risk occur.
Here's a few examples:
- I have a risk and the plan should the risk occur has been though
out in detail. I want to put the tasks into the schedule so we ca
track what will happen to the project if the risk occurred at an
given time. Let's make it easy and say it might happen at one time
say when the clocks change... did it impact the system's schedule? I
yes, invoke risk plan. While the risk does not happen the dependen
tasks can start. (in reality they aren't always that easy and we nee
to move the risk around in time, keep the dependencies locked in, bu
as it probably won't happen I need to keep the resources available t
start the tasks as if the risk plan wasn't there)
- I am due to go on extended leave in November. If the project doe
not finish in time then I need to schedule handover tasks in October
I would like these tasks to not affect the total cost of the projec
or the overall time line unless a key milestone passes a deadline.
- The project is at risk of exceeding a threshold. We want to look a
reducing scope to meet the threshold. We don't want to lose all th
values for the tasks for a particular deliverable but want t
effectively cancel them to see the impact (I know I could just mov
the tasks to a different phase further down but that will mess up th
tracking views and EVA and is not what I want to show).
I know that I can do a lot of this manually and I can plan for th
worst case every time, but it would be so nice if MS Project could le
me put the scenarios into the schedule and alert me accordingly.
Thanks in advance for any advice that any of you may be able t
provide.
Regards, Andrew