Is there anyway to prevent PM to overwrite actual work entered by resources
from Project Pro ??
We just implemented the bonus system for all team member based on the actual
work entered by resources.
If total actual-work less than or equal to baseline work, it means there
will be bonus project for all team members.
In this case, all team members will try to decrease their actual work to
achieve the bonus project and PM have the chance to do this cheat to make
his/ team members get the bonus project.
Any help very appreciated.
Is there anyway to prevent PM to overwrite actual work entered by resources
from Project Pro ??
We just implemented the bonus system for all team member based on the actual
work entered by resources.
If total actual-work less than or equal to baseline work, it means there
will be bonus project for all team members.
In this case, all team members will try to decrease their actual work to
achieve the bonus project and PM have the chance to do this cheat to make
his/ team members get the bonus project.
Any help very appreciated.