Prevent Re-Setting of Baseline

J

JudithJubilee

Hello there,

Is there anyway of disabling the Set Baseline command once a Baseline has
been set but still allow people to interact with the project? I am using
Project 2003.

Thanks in advance

Judith
 
J

Jan De Messemaeker

Hi,

Not as such. You could detect the re-setting by the beforesave event and
refuse the saving of the project but that would also make other changes
disappear...

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 