Angela
I know this question seems to have been asked before, but I can’t seem to
find an answer that responds directly to my needs. We have a project with
contractual dates that need to be classed as the baseline date. I’ve
baselined the project and now have variations to add where the finish date is
later than the baseline date. How can I re-baseline, keeping the original
baseline dates instead of the baseline picking up the new finish dates? The
only way I can think of doing this is by using my Finish column for the
contractual dates and adding a customised Finish column as my projected
finish, but I’m concerned about the impact to formulas I already have in this
plan that uses the Finish column as part of its formula.
Any suggestions would be appreciated.
Thanks
Angela
find an answer that responds directly to my needs. We have a project with
contractual dates that need to be classed as the baseline date. I’ve
baselined the project and now have variations to add where the finish date is
later than the baseline date. How can I re-baseline, keeping the original
baseline dates instead of the baseline picking up the new finish dates? The
only way I can think of doing this is by using my Finish column for the
contractual dates and adding a customised Finish column as my projected
finish, but I’m concerned about the impact to formulas I already have in this
plan that uses the Finish column as part of its formula.
Any suggestions would be appreciated.
Thanks
Angela